Dashboard
Open Dashboard from the sidebar (or home on mobile).
- Set the As of date (and optionally Today) so charts reflect that date.
- Review chart cards: Drawings, Schedule, Tasks, Team (managers / supervisors), Notifications.
- Use View on a card to jump to that area of the app.
- Check My Tasks This Week, compact notifications, and the activity feed in the side column.
- Adjust refresh interval if you want periodic reloads.
Note: Numbers come from live project data you are allowed to see. Empty charts mean there is no data yet for that module, not that the feature is broken.
Drawings
Drawings is the project drawing library (register and gallery) and where you open sheets to place work. Field work can also open the same drawing viewer from Tasks or Briefing when a task already has a location.
Upload and revise drawings
- Open Drawings.
- Upload PDF drawings (bulk upload may be available depending on your role).
- Wait until processing finishes (status on the drawing).
- Add a revision when the issued drawing changes (plan limits may apply).
Drawing viewer
Open a drawing to:
- Pan and zoom the sheet
- Place or select pins for point-based tasks
- Work with zones for area-based work
- Use layers, notes, markup, and measure tools as shown in the toolbar
- Compare or browse revisions when available
Create work from the drawing
- Place a pin or select a zone.
- Create a task from the pin / zone flow (or place an existing task).
- Fill in title, assignees, dates, and classification fields as required.
- Save. The task appears under Tasks and on the drawing.
Tip: Use pin filters to focus on status or type when the sheet is busy.
Tasks
Open Tasks from the sidebar.
Views and toolbar
| Control | Purpose |
|---|---|
| List | Table-style task register (includes Owner and Assignee columns where shown) |
| Kanban | Board by status |
| Work Plan | Calendar board of work from published weekly Work Plans (see Schedule) |
| All / Schedule / Non-Schedule | Tabs that limit the list (and the stats strip) to that source |
| Lookahead | Limit the register to a week window or custom dates |
| Filters | Status, priority, assignee, schedule vs non-schedule source |
| Classification | Filter by classification facets |
| Saved Views | Reuse saved filter combinations |
| Search | Find tasks by text |
Stats strip (List)
Above the List register, summary chips (Total, Not Started, In Progress, On Hold, Delayed, Completed, Unassigned, Due This Week) show counts for the active tab (All / Schedule / Non-Schedule). Click a chip to filter the list; click the active chip again to return to Total.
Note: Importing a programme into Schedule does not automatically fill Tasks. Commit a Work Plan on Schedule, then Publish to Tasks. Until then, schedule-only leaves may not appear (or stay locked) in the register. The Work Plan view shows an empty state until something has been published.
Owner and assignees
| Role | Meaning |
|---|---|
| Owner | The one person accountable for the work (quality and follow-through) |
| Assignee(s) | People who do or update the work in the field |
These fields are independent: someone can be both, but assigning a person as Owner does not auto-add them as Assignee (and the reverse). Prefer Owner for accountability; use Assignees for who is carrying out the work.
Create and update a task
- Use New Task from Tasks, or create from a drawing pin or zone.
- Enter title, status, priority, dates, Owner, assignees, and classification as required.
- Open a task to edit details, add comments (with @mentions where supported), and upload media.
- Move status through your workflow (for example not started → in progress → completed). Respect blocked / on-hold states when used.
Managers may also configure Task Templates and Task Classification under Project Settings.
Warning: Completing or reassigning work can notify other members. Confirm Owner and assignees before saving.
Schedule
Open Schedule (shown only if your role can view schedule).
Header tools
| Control | Purpose |
|---|---|
| Revision selector | Choose which schedule revision you are viewing |
| Filter | Status, discipline, priority, assignee / owner, critical path, milestones |
| Sort | Grouping / sort options such as building or level |
| Views | Scale (weeks/days), hierarchy, Gantt on/off, zoom |
| Actions (+) | Import, export, delete revision (as permitted) |
Lookahead and Work Plans
The planning strip above the grid is for short-term windows — separate from the Tasks Lookahead filter.
| Control | Purpose |
|---|---|
| Lookahead presets | Full schedule, or a short window (for example 1W / 2W / …) or Custom dates |
| Span (Work Plan board) | Today / Week / Month, with previous / next — focuses the board day columns |
| Save | Save the current window as a named lookahead, or open a saved lookahead / committed Work Plan |
| Work Plan | Commit activities in the current date window as a Work Plan (does not publish to Tasks by itself) |
| Full screen | Hide the app sidebar and headers so the schedule fills the screen (toggle in the Schedule toolbar) |
Typical short-term flow
- Set a lookahead or date window so the grid shows the period you care about.
- Optionally open Save, accept or edit the suggested name, and save the lookahead for reuse.
- Choose Work Plan to commit. In the commit dialog, select the overlapping activities to include, then proceed. The plan opens as its own tab beside the main schedule.
- On a committed Work Plan tab, use Publish to Tasks when the site team should see that work under Tasks (List, Kanban, and Work Plan). Use Unpublish to reverse publish for items that are still pure schedule mirrors (field progress already captured is kept). Delete removes the Work Plan record when permitted.
- Open committed plans again from Save → Work Plans → Open.
- On the Work Plan board, use Span (Today / Week / Month) to focus the day columns without leaving the plan.
Note: Commit locks in the plan selection for that period. Publish to Tasks is the step that materialises day-to-day Tasks. Import alone does not unlock the whole programme into Tasks.
Working with the schedule
- Import from Excel / CSV with the smart import mapper when starting from an external programme, or create activities in the table.
- Edit dates, names, Owner, assignees, and related fields inline where you have edit rights.
- Toggle the Gantt chart beside the table; zoom as needed. The board and Gantt stretch to the available width; weekends appear in the range and are shown greyed when they are non-working days.
- Use predecessors where your process requires them.
- Export Excel, CSV, Gantt PDF, or P6 XER when those options appear.
Project Calendars (working days and holidays) are configured under Project Settings → Calendars and affect scheduling behaviour.
Briefing, Coordination, and Diary
These sidebar areas support day-of and site execution (visibility depends on your project role). Briefing and Coordination share a spatial layout: drawings for the covering Work Plan, an overlay Work Plan board, and (on Coordination) a right panel for the meeting. Use Full screen in the page toolbar to hide the app chrome while you run the meeting or briefing (on by default for Briefing and Coordination; available on Schedule too).
| Screen | What it is for |
|---|---|
| Briefing | Live Work Plan on drawing + board; publish a briefing record; browse Past briefings |
| Coordination | Same spatial shell for the meeting day; attendance, notes, actions, and board-linked blockers |
| Diary | Capture site diary entries linked to the day’s work |
Typical path: plan and commit on Schedule → Publish to Tasks for the register → use Briefing / Coordination / Diary for the live site day.
Briefing
- Open Briefing. The default Briefing mode shows the committed Work Plan that covers the selected date on the drawing and bottom board.
- Change the date if you need another day’s covering plan.
- Use Publish to create a briefing record: choose the committed Work Plan, confirm the title (defaults to
Wks Mon-DD-YY - Mon-DD-YY), and select Audience members. - Open Past to search and filter published briefings by month; select one to return to the live spatial view for that plan period.
Coordination
- Open Coordination. The shell loads the covering Work Plan for the selected date (one meeting per project day).
- In the right panel, mark Attendance, enter notes, then Save notes & attendance.
- Add an action (title, assignee, due date, decision). Use Link to Task, then click a task on the Work Plan board to link it. Optionally Flag as blocker (meeting flag only — escalate to On Hold in Task Details if the field task should change status).
- Mark actions done or cancelled when closed; that clears the meeting blocker flag.
- Close / Reopen the meeting when finished. To review a past day, change the date picker — there is no separate Past hub like Briefing.
Tip: Field roles often see Briefing and Diary even when Team or full Schedule edit is hidden. Board Span (Today / Week / Month) on the Work Plan board focuses day columns the same way as on Schedule.
Team
Team page
If Team appears in the sidebar, open it for capacity / workload views for the project week (feature and role dependent).
Team and Roles (settings)
Invites and role changes: Gear → Project Settings → Team and Roles. See Setting Up.
Reports
Open Reports when enabled for your plan and role.
- Choose a report type and audience preset if offered.
- Set filters, columns, and sort as needed.
- Generate and download PDF or Excel.
Note: Progress / standard reports may require Starter or Pro. Task-level exports from a single task can still be available on more plans — follow what the UI offers.
Projects
- Use the project switcher in the header to change project.
- Open Projects in the sidebar for your portfolio and to create or continue setup.
- Incomplete setup may show a banner until key steps are done.
Notifications
- Open the bell in the header for recent notifications.
- Unread items are highlighted; open an item to go to the related work when a link is provided.
- Gear → Account Settings → Notifications to turn event types on or off.
AI Assistant
If the Assistant control appears (feature flag / plan):
- Open Assistant from the header.
- Ask questions about the current project within your access rights.
- Treat answers as guidance; confirm important decisions in the source screens (drawings, tasks, schedule).
Warning: The assistant must not expose data you cannot already access. If a reply looks wrong, check the underlying task or drawing.
Feedback and help
- Gear → Help — opens help in the app with links to https://help.coordasite.com
- Gear → Feedback — send feedback to the product team
- Email support@coordasite.com
Mobile tips
- Use bottom navigation for main areas; use the gear for settings, theme, language, and sign out.
- Prefer Tasks, Drawings, Briefing, and Diary on site; use desktop for large schedule edits, Work Plan commit/publish, and complex drawing markup.
- Add the site to your home screen for quicker access.
- Watch the offline indicator; sync when you are back online before assuming everyone else sees your edits.
Best practices by role
Field / tradesperson
- Check My Tasks, Briefing, and notifications daily.
- Update status and add photos when work finishes; use Diary when your team records site notes there.
- Open the drawing pin when you need context on location.
Supervisor
- On Schedule, set a lookahead, Commit a Work Plan for the week, then Publish to Tasks.
- Use Tasks List / Work Plan, the All / Schedule tabs, and stats chips for the week ahead; keep Owner and assignees accurate.
- Run Briefing (publish with audience) and Coordination (attendance, actions, Link to Task on the board). Clear blocked field tasks in Task Details when needed; meeting Flag as blocker alone does not put a task On Hold.
- Use Team views when available to spot overload.
Manager / admin
- Keep drawings on the latest revision.
- Align Calendars before major schedule imports.
- Treat Publish to Tasks as the gate from programme to site register — do not expect import alone to flood Tasks.
- Use Owner for accountability and Assignees for who executes; Saved Views and classification for consistent reporting.
- Review Billing and Permissions only with the right org / plan access.